Church Building Works – a Progress Report

Mar 27, 2018 | Uncategorised

Much progress is being made off site with the church building project and in church things are progressing well after the delay caused by the bad weather.

The beautiful oak door to the lobby area and toilets and the panel above are now in place as well as the oak cornicing on the two new Vestries. New radiators are now in and functioning, which is a welcome advancement after a few weeks of sitting in a very cold church.

The old parquet flooring has been removed from the back of the nave ready for laying  the new oak strip flooring and the fitting of the tracks for the moveable servery. The old cupboards have been removed from the south porch and a new sink and dishwasher have been installed.

Helen V

 